Material Takeoff Template: Free Template for Contractors

Material Takeoff Template: Free Template for Contractors
Share LinkedIn Facebook

Quick Answer

A material takeoff lists every material needed for a job with its quantity, unit of measure and cost. To do one, break the job into sections, measure quantities from plans or a site visit, add a waste factor, convert to purchasable units (boxes, sheets, bundles), price each line from current supplier quotes and total it. Have someone check the math, then use the takeoff to build your bid, order materials and compare actual use after the job.

Every accurate bid starts with an accurate count of materials. Miss 20 sheets of drywall or a box of fittings and the profit disappears, or the crew sits waiting for a second delivery. A material takeoff is how contractors turn plans or a site walk into a list of exactly what to buy.

This guide includes a free material takeoff template and explains how to measure quantities, add waste, convert units, price materials, check your work and use the takeoff for bidding, ordering and job costing.

What Is a Material Takeoff?

A material takeoff, also called a quantity takeoff or material list, is a detailed list of materials needed to complete a project. It is "taken off" the drawings or site measurements. Each line shows the item, specification, quantity, unit and cost.

TermMeaning
TakeoffMeasuring and counting materials from plans or the site
EstimateTakeoff plus labor, equipment, subcontractors, overhead and profit
Bid or quoteThe price you give the customer
Purchase orderThe order you send to suppliers

Free Material Takeoff Template

Material Takeoff
Project: __________  |  Customer: __________  |  Plans / revision: ______  |  Date: ______
Prepared by: __________  |  Checked by: __________

SectionItem / specMeasured qtyUnitWaste %Order qtyPurchase unitUnit costLine totalSupplier
Framing2x4x8 SPF studea10%ea
Drywall1/2" 4x8 sheetsq ft10%sheet
Fasteners1-5/8" drywall screwssheet—box
Subtotal
Sales tax / delivery
Total materials

Step-by-Step: How to Do a Takeoff

  1. Gather documents: plans, specs, site photos and scope of work.
  2. Break the job into sections by area, phase or trade.
  3. Measure each section: lengths, areas, volumes and counts.
  4. List materials needed for each measurement.
  5. Add waste factors for cuts, breakage and mistakes.
  6. Convert to purchase units like sheets, boxes or bundles.
  7. Price each line from current supplier pricing.
  8. Add tax and delivery where they apply.
  9. Have someone check quantities and math.

Measurement Types

TypeUnitExamples
Counteach (ea)Doors, fixtures, outlets, plants
Linearlinear feet (LF)Trim, pipe, fencing, gutters, edging
Areasquare feet (SF) or squaresDrywall, flooring, roofing, sod, paint
Volumecubic yards (CY)Concrete, mulch, gravel, fill
Weighttons or poundsRebar, asphalt, stone

Write the unit on every line. Mixing square feet and square yards, or linear feet and pieces, is one of the most common takeoff errors.

Common Takeoff Formulas

CalculationFormula
Wall areaWall length × height − large openings
Floor areaLength × width
Concrete (CY)Length × width × depth (ft) ÷ 27
Mulch or gravel (CY)Area (SF) × depth (in) ÷ 324
Studs (16" on center)Wall length (ft) × 0.75 + 1, plus corners and openings
Roofing squaresRoof area (SF) ÷ 100
Paint (gallons)Area × coats ÷ coverage per gallon

Always confirm coverage rates and sizes with the manufacturer or supplier, since products vary.

Waste Factors

Waste covers cuts, breakage, mistakes and pattern matching. Typical ranges depend on the material and layout:

MaterialTypical waste range
Drywall10–15%
Framing lumber10–15%
Tile (straight lay)10%
Tile (diagonal or pattern)15–20%
Flooring5–10%
Roofing shingles10–15%
Concrete5–10%

These are common starting points, not rules. Track actual use on completed jobs and adjust your own waste factors.

Converting to Purchase Units

You measure in square feet but buy in sheets, boxes and bundles. Convert every line and round up:

Example: A room has 1,150 SF of wall and ceiling. Add 12% waste = 1,288 SF. A 4x8 sheet covers 32 SF. 1,288 ÷ 32 = 40.25, so order 41 sheets.

Pricing Materials

Record supplier and price date in the takeoff so you can recheck before ordering. See the vendor list template.

From Takeoff to Bid

The takeoff is the material part of your estimate. Add labor hours, equipment, subcontractors, permits, overhead and profit to reach your price. Keep the takeoff attached to the bid so you can answer customer questions and price change orders quickly. See the contractor quote template and the bid log.

From Takeoff to Purchase Order

When you win the job, the takeoff becomes your order list. Group lines by supplier and delivery date, confirm quantities against any scope changes and send purchase orders. Check deliveries against the order when they arrive. See the receiving log.

Takeoffs by Trade

TradeKey takeoff items
FramingStuds, plates, headers, sheathing, fasteners
DrywallSheets, screws, tape, mud, corner bead
PaintingGallons by color and sheen, primer, caulk, tape, plastic
FlooringFlooring SF, underlayment, transitions, trim
RoofingSquares, underlayment, starter, ridge, flashing, nails
PlumbingPipe by size and length, fittings, valves, fixtures
ElectricalWire by gauge, boxes, devices, breakers, fixtures
LandscapingPlants by size, mulch CY, soil, edging LF, stone
ConcreteCY, rebar, mesh, forms, vapor barrier

Checking Your Takeoff

A second set of eyes catches more mistakes than rechecking your own work. Even a quick review of the biggest lines is worth the time.

Comparing Takeoffs to Actual Use

After the job, compare what you ordered with what you used and returned. If you always run short on one material or return a lot of another, adjust your waste factors. Credit unused materials back to the job so job costs stay accurate. See how to track labor costs by job.

Example: A Basement Finish

A small remodeling company kept running short on drywall and trim on basement jobs, which meant extra supply runs and idle crew time. The owner started using a takeoff template with sections for each room, a 12% drywall waste factor and a line for small items like screws and corner bead. Supply runs dropped, and comparing takeoffs to actual use showed that trim needed a higher waste factor for the company's typical basement layouts.

Common Takeoff Mistakes

Material Takeoff Checklist

StepDone?
Gather plans, specs and scope
Break job into sections
Measure and label units
Add waste factors
Convert to purchase units
Price with current quotes
Review and check
Compare to actual use after the job

Sample Completed Takeoff: Small Bathroom

ItemMeasuredWasteOrderUnit costTotal
1/2" moisture-resistant drywall320 SF12%12 sheets$18.00$216.00
Wall tile 12x2490 SF15%104 SF (8 boxes)$32.00/box$256.00
Floor tile 12x1245 SF10%50 SF (5 boxes)$22.00/box$110.00
Thinset——4 bags$19.00$76.00
Grout——2 bags$24.00$48.00
Cement board45 SF10%4 sheets$14.00$56.00
Subtotal$762.00

This sample uses made-up prices and quantities. Your coverage rates, box sizes and prices will differ, so always check product labels and current supplier quotes.

Organizing a Takeoff

How you organize a takeoff makes it easier to check, price and reuse. Common ways to group lines:

Organize byBest for
Room or areaRemodels and residential work
PhaseProjects built in stages, like foundation, framing, finishes
TradeJobs with several subcontractors
SupplierBuilding purchase orders
Cost codeJob costing and comparing to budget

Many contractors measure by area, then sort by supplier when it's time to order. A spreadsheet makes re-sorting easy.

Plan Reading Tips

Takeoffs From a Site Visit

Many small jobs don't have plans. For these, take measurements and photos on site and sketch the layout with dimensions. Measure twice, note ceiling heights and existing conditions and photograph anything that could affect materials, like uneven floors or damaged framing. Write down what you didn't measure so it can be checked before ordering.

Small Items Checklist

Small items are easy to forget and add up fast. Before finishing a takeoff, check for:

Some contractors add a small percentage for consumables instead of listing every item. Either works, as long as you do it consistently.

Handling Plan Revisions

When plans change, update the takeoff right away and note the revision. Highlight changed lines and recheck the total. If the change happens after a bid is accepted, the difference becomes part of a change order. See the construction change order form.

Reusing Takeoffs

Save completed takeoffs by job type. A takeoff from a similar past job is a great starting point and a quick check on a new one. Over time, you'll see typical material costs per square foot or per job type, which helps with quick ballpark pricing before a full takeoff.

Takeoff Accuracy and Profit

Materials are often a large share of job cost. A small takeoff error on a big line can wipe out the profit on the whole job. Consider a job with $20,000 in materials and a 10% profit margin on a $60,000 price. Missing just 5% of the materials costs $1,000, which is one-sixth of the expected profit. Over a year of jobs, small misses add up.

ErrorResult
Under-countingLost profit, extra supply runs, idle crews
Over-countingHigher bids, lost jobs, leftover inventory
Wrong specificationReturns, delays and rework
Old pricesMargin squeezed when you buy

Takeoff Software vs. Spreadsheets

Digital takeoff tools let you measure directly on PDF plans and can speed up large or complex projects. A spreadsheet takeoff works well for many small contractors: it's flexible, easy to reuse and easy to share with suppliers. Whichever you use, the process is the same: measure carefully, label units, add waste, price with current quotes and check the work.

Working With Suppliers on Takeoffs

Many suppliers will review a takeoff or even prepare one from your plans, especially for lumber, roofing or plumbing packages. This can be a helpful double check, but review their numbers against your own. Suppliers may round up generously or miss items outside their product lines. You're still responsible for what's in your bid.

Material Takeoff Quick Reference

RememberWhy
Label every unitPrevents unit mix-ups
Round up to purchase unitsYou can't buy part of a box
Note plan revisionAvoids pricing old drawings
Date every priceKnow when to recheck
List small itemsThey add up
Compare to actual useImproves the next takeoff

Keep this list next to your template and run through it before every bid goes out.

Who Should Do the Takeoff

In small companies, the owner or estimator usually does the takeoff. As you grow, a project manager or lead carpenter may take over certain trades. Whoever does it, the person checking should be someone else. Crew leads make great checkers because they know how materials actually get used on site, including the waste and extra pieces the plans don't show.

Track the time spent on takeoffs too. Estimating time is part of your overhead, and knowing how long takeoffs take helps you decide which jobs are worth bidding.

Getting Started

Pick one recent job and do a takeoff for it using the template, then compare with what you actually bought. The differences will show you where your process needs work. Fix those spots, save the template and use it on your next bid.

A good takeoff is one of the simplest ways to protect your margins. It takes discipline more than special skill: careful measuring, consistent units, honest waste factors and a second set of eyes before the number goes into a bid.

Start with the template above, adjust the sections for your trade and save it as your standard. Every job you finish makes the next takeoff a little faster and a little more accurate.

Bid and Build Jobs With Updoot

Updoot's purchasing turns your takeoff into purchase orders, project management keeps the job organized and the employee time clock tracks labor against the job.

Related Reading

Bid Log →

Contractor Quote Template →

Purchasing Software →

Frequently Asked Questions

What is a material takeoff? ▶
A list of every material needed for a job with quantities, units and costs, measured from plans or the site.
What is the difference between a takeoff and an estimate? ▶
A takeoff covers materials; an estimate adds labor, equipment, subs, overhead and profit.
How much waste should I add? ▶
It depends on the material; many contractors start around 5–15% and adjust based on actual use.
How do I calculate concrete in cubic yards? ▶
Length × width × depth in feet, divided by 27.
Should I round up quantities? ▶
Yes, to full purchase units.
How do I check a takeoff? ▶
Have someone else review areas, units, waste, small items and prices.
Can I use a spreadsheet for takeoffs? ▶
Yes. A spreadsheet works well and makes it easy to reuse templates.
What should I do after the job? ▶
Compare ordered versus used materials and adjust waste factors.
What should I include besides main materials? ▶
Fasteners, adhesives, consumables, protection and disposal.
How do I handle plan revisions? ▶
Update the takeoff, note the revision and use a change order if the bid was already accepted.
Is takeoff software required? ▶
No. Many small contractors use spreadsheets; the process matters more than the tool.
Who should check a takeoff? ▶
Someone other than the person who did it, ideally a crew lead who knows how materials are used on site.