Construction Change Order Form: Free Template for Contractors

Construction Change Order Form: Free Template for Contractors
Share LinkedIn Facebook

Quick Answer

A construction change order is a written agreement between a contractor and customer to change the original scope, price or schedule of a job. Include the job and contract details, a clear description of the change, the reason, the cost breakdown for labor and materials, the effect on the schedule, the new contract total and signatures from both sides. Get the change order signed before starting the extra work, and follow any change order process in your contract.

"While you're here, can you also..." Every contractor hears it. Customers change their minds, hidden problems show up behind walls and plans have gaps. Without a written change order, extra work leads to arguments about price, missed payments and shrinking profit.

This guide includes a free construction change order form and explains when you need one, what to include, how to price changes, how to get them signed and how to track them through the job.

Note: This is general information, not legal advice. Your contract and state law may set requirements for change orders, especially on home improvement jobs. Have an attorney review your contract and change order form.

What Is a Change Order?

A change order is a written amendment to a construction contract. It documents a change in the work, the price, the schedule or all three, and both the contractor and the customer sign it. Once signed, it becomes part of the contract.

Common reasons for change ordersExamples
Customer requestsUpgrade to tile, add an outlet, move a wall
Hidden conditionsRot, water damage, outdated wiring found during demo
Design changesArchitect revises plans
Code or inspection requirementsInspector requires additional work
Material availabilitySpecified product discontinued; substitute needed
Scope removedCustomer decides to skip part of the work (a deductive change order)

Free Construction Change Order Form

Change Order # ______
Date: ______  |  Job: __________  |  Address: __________
Customer: __________  |  Original contract date: ______  |  Contract #: ______
Requested by: ☐ Customer ☐ Contractor ☐ Architect/Engineer ☐ Inspector

Description of Change

Describe the change clearly, including location and materials: __________________________________________

Reason for change: __________________________________________

Cost Breakdown

ItemQuantityUnit costTotal
Labor (hours × rate)
Materials
Subcontractor
Equipment rental
Permits or fees
Overhead and profit
Credit for work removed( )
Change order total

Contract Summary

Amount
Original contract amount
Previous approved change orders
This change order
New contract total

Schedule Impact

Days added (or removed): ______  |  New estimated completion date: ______

Payment Terms

☐ Due with next progress payment   ☐ Due before work begins   ☐ Due at completion of change

Signatures

By signing, both parties agree to the change in scope, price and schedule described above. All other terms of the original contract remain in effect.

Customer: __________  |  Date: ______
Contractor: __________  |  Date: ______

When You Need a Change Order

A good rule: if it changes what you're building, what it costs or when it will be done, write it down and get it signed.

Writing a Clear Description

VagueClear
"Upgrade bathroom tile""Replace specified 12x12 ceramic floor tile with customer-selected 12x24 porcelain tile (style #, color) in primary bath, approx. 65 sq ft, including additional thinset and labor."
"Fix rot""Remove and replace approximately 12 linear feet of rotted sill plate along the north wall, discovered during demolition. Includes treated lumber, fasteners and labor."
"Add outlets""Add two duplex outlets on the kitchen island, including wiring from the existing circuit, boxes and covers."

Attach photos, sketches or product specs when they help explain the change.

Pricing a Change Order

  1. Labor: estimate hours for each trade and multiply by your rates.
  2. Materials: use current supplier pricing, plus waste.
  3. Subcontractors: get their price in writing.
  4. Equipment and permits: include any rentals or extra permit fees.
  5. Overhead and profit: apply your standard markup, or what your contract specifies.
  6. Credits: subtract work or materials no longer needed.
  7. Schedule costs: consider extra supervision or general conditions if the job runs longer.

Use the same pricing method you used for the original estimate so customers see consistent numbers. See the contractor quote template.

Getting Change Orders Signed

If urgent work can't wait, such as stopping an active leak, get written approval by email or text describing the work and the pricing method, then follow up with a formal change order as soon as possible.

Hidden Conditions

Hidden problems are a common source of disputes. Reduce them by:

Tracking Change Orders

CO #DateDescriptionAmountDaysStatusSignedBilledPaid
1☐ Pending ☐ Approved ☐ Rejected☐☐☐
2☐ Pending ☐ Approved ☐ Rejected☐☐☐
3☐ Pending ☐ Approved ☐ Rejected☐☐☐

A change order log keeps the running contract total accurate and makes sure every approved change gets billed. Missed change orders are one of the most common ways contractors lose money on a job.

Billing for Change Orders

Add approved change orders to your next invoice or progress billing as separate line items, referencing the change order number. Customers are more likely to pay promptly when they can match each charge to a signed document. See project billing and invoice software for contractors.

Change Orders With Subcontractors

When a change affects a subcontractor's work, get their price in writing and issue a matching change order to the sub. Don't let subs start extra work until the customer change order is signed, or you may end up paying for work you can't bill.

Example: A Remodeling Contractor

A remodeler often agreed to small changes on site and planned to "settle up at the end." At closeout, customers remembered the changes differently and pushed back on the extra charges. He started using a one-page change order on a tablet, with photos and e-signature, before doing any extra work. Disputes at final billing nearly disappeared, and change order revenue that used to slip away now shows up on every job.

Common Change Order Mistakes

Change Order Checklist

StepDone?
Include a change order process in your contract
Describe the change clearly with photos or specs
Price labor, materials, subs and markup
Show schedule impact and new contract total
Get signatures before starting work
Log every change order
Bill approved changes on the next invoice

Change Order Clauses in Your Contract

Your original contract should explain how changes will be handled. Common provisions include:

Having these terms in the contract makes change orders routine instead of a negotiation every time. Have an attorney review your contract language.

Fixed Price vs. Time and Materials Change Orders

Fixed priceTime and materials
How it worksAgreed price before workBilled for actual hours and materials
Best forClear, defined changesUncertain scope, like hidden damage
Customer comfortKnows the cost up frontNeeds a not-to-exceed amount to feel safe
PaperworkPrice on the change orderTime sheets and material receipts

For time and materials changes, include your rates and a not-to-exceed amount, and track hours carefully.

Change Order Request Form for Customers

Some contractors give customers a simple request form, so new ideas come in writing before they're priced.

FieldAnswer
Customer name and job
What would you like to change?
Location in the project
Photos or examples attached?☐
Is this needed now or can it wait?
Customer signature and date

The request isn't an approval. Price it, write the change order and get it signed before doing the work.

Talking With Customers About Changes

Sample: "That's a great idea, and we can do it. Because it's outside the original scope, I'll write up a change order with the cost and any effect on the schedule. Once you sign it, we'll get started."

Being upfront and friendly about change orders keeps them from feeling like surprise charges. Customers appreciate knowing the cost before deciding.

Change Orders and Profit

Change orders can help or hurt your margin. Priced and billed correctly, they add profit. Done for free or forgotten, they quietly eat into it. Review change orders on every completed job: how many there were, how much they added and whether any work was done without one. See how to track labor costs by job.

Digital Change Orders

Sample Completed Change Order

FieldExample
Change order #3
JobKitchen remodel, 123 Main St.
Requested byCustomer
DescriptionAdd under-cabinet LED lighting under four upper cabinets, with a dimmer switch next to the existing light switch
Labor6 hours electrician
MaterialsLED strips, drivers, dimmer, wire, boxes
MarkupPer contract
Schedule impact+1 day
New completion dateAdjusted by one day
PaymentDue with next progress payment

This sample is for illustration. Your pricing and terms will depend on your contract and costs.

Rejected and Pending Change Orders

Not every change order gets approved. If the customer declines, note it in the log and continue with the original scope. For pending change orders, set a deadline for a decision, especially when the change affects the schedule or material orders. Don't let pending changes hold up the rest of the job without telling the customer how the delay affects completion.

Change Orders on Commercial Jobs

Commercial contracts often have formal change order procedures, including written requests for proposals, required forms, approval by an owner's representative or architect and strict notice deadlines for claims. Missing a notice deadline can cost you the right to be paid for extra work, so read the change order section of every commercial contract carefully.

Change Order Quick Tips

Training Your Crew on Change Orders

Customers often ask crew members, not the owner or project manager, for extra work. Train every crew lead on a simple rule: be friendly, say yes to pricing it, but don't start anything outside the plans until a change order is signed.

Crew script: "Good idea. That's outside our current scope, so I'll pass it to [project manager], who'll send you the price and timing to approve. Once it's signed, we can do it."

Write the rule into your job site procedures and review it at the start of every job. Crews who do "small favors" for free can quietly cost a job its profit, and they leave you without paperwork if the customer later disputes what was agreed.

Change Order Records to Keep

Change Orders and Permits

Some changes require a permit revision or an extra inspection. Check whether the change affects your permit before starting, include any permit fees in the change order and note the extra inspection in the schedule impact. Inspections that are missed because of an unpermitted change can cost far more than the change itself.

Reviewing Change Orders With the Customer at Closeout

At the final walkthrough, review the change order log with the customer: every approved change, its price and the final contract total. Pair it with the punch list so the customer sees the full picture before the final invoice.

Getting Started on Your Next Job

  1. Add a change order clause to your contract template.
  2. Save the change order form on your phone or tablet.
  3. Start a change order log for each job.
  4. Train crew leads on the "price it, sign it, then do it" rule.
  5. Review change orders at every job closeout.

Once the habit is in place, change orders stop feeling like a hassle and start protecting both you and your customers on every job.

Manage Jobs and Changes With Updoot

Updoot's project management keeps change orders, tasks and documents with each job, the employee time clock records crew hours on change order work and the invoice generator helps you bill approved changes. See also the construction punch list.

Related Reading

Construction Punch List →

Contractor Quote Template →

Project Management →

Frequently Asked Questions

What is a construction change order? ▶
A written, signed amendment to a contract that changes the scope, price or schedule of a job.
When do I need a change order? ▶
Whenever the work, price or schedule changes from the original contract.
What should a change order include? ▶
A description, reason, cost breakdown, schedule impact, new contract total and signatures.
Should I start work before a change order is signed? ▶
No. Get it signed first, except for true emergencies documented in writing.
How do I price a change order? ▶
Estimate labor, materials, subs, equipment and permits, add markup and subtract credits.
What is a deductive change order? ▶
A change order that removes work and reduces the contract price.
How do I bill change orders? ▶
Add approved change orders as separate lines on your next invoice.
Are change orders required by law? ▶
Some states have rules for home improvement contracts. Check your contract and state law.
What should my contract say about change orders? ▶
That changes must be written and signed, how they're priced, markup, hidden conditions and payment timing.
When should I use time and materials pricing? ▶
For uncertain work like hidden damage, with rates and a not-to-exceed amount.