DuPont Schedule: How the 4-Week Rotation Works, With a Free Generator
Build the schedule once, share it with everyone. Who’s working, who’s out and who swapped, all in one view.
14 days free. No credit card needed. Cancel anytime.

Quick Answer
DuPont schedule basics: four crews work 12-hour shifts on a 28-day cycle of 4 nights, 3 off, 3 days, 1 off, 3 nights, 3 off, 4 days and 7 off. One crew is always on days and one on nights. Each employee averages 42 hours a week and gets a full week off every 28 days. The trade-off is a hard week of up to 72 hours with a quick switch from days to nights, and weekly hours that swing enough to create 16 to 48 overtime hours per employee every cycle, depending on where the cycle starts relative to the workweek.
DuPont schedule questions usually start with the week off and end with the week nobody likes, so the fastest way to understand it is to see it. Use the free DuPont schedule generator below to lay out all four crews, check that every day and night shift is covered and see exactly how many hours each crew works in every payroll workweek. Then keep reading for how the 28-day rotation works, what the 72-hour week does to overtime and how to decide whether DuPont fits your operation.
The DuPont schedule is a 12-hour rotating shift pattern for operations that never stop: chemical plants, refineries, power plants, paper mills, hospitals and emergency services. It covers every hour of the week with four crews, just like the Pitman schedule, but it trades Pitman's short stretches for something employees love: seven days off in a row every four weeks, without using a single hour of PTO.
Free DuPont Schedule Generator
The generator starts on the DuPont pattern. Set the start date to the first day of your rotation, choose the day your payroll workweek starts and look at the "Hours by Workweek" table. On DuPont, those two choices make a bigger difference to overtime than on almost any other schedule.
Shift Schedule Generator
Pick a pattern and a start date. The schedule, coverage check and weekly hours update as you change the settings. Print it or copy it into Excel or Google Sheets.
Schedule Settings
Pattern Summary
Schedule
Hours by Workweek
Planning tool only. This generator lays out a repeating shift pattern and estimates hours in each payroll workweek, based on the workweek start day you choose, and assumes the rotation repeats without changes. It is not legal or payroll advice. Overtime, break, rest period and predictive scheduling rules vary by state and city, and union contracts may set their own rules. Confirm the schedule with your payroll provider or an employment attorney before you publish it.
What Is a DuPont Schedule?
A DuPont schedule is a 24/7 rotating shift pattern in which four crews work 12-hour shifts over a 28-day cycle, rotating between day shifts and night shifts. On any given day, one crew works the day shift, one works the night shift and two are off. Each crew works 14 shifts every 28 days, which is 168 hours, or an average of 42 hours a week.
The schedule is named after the DuPont chemical company, where it is widely credited as starting in the middle of the last century. Chemical and process plants needed people on site around the clock, and moving from three 8-hour shifts to two 12-hour shifts let four crews cover all 168 hours of the week.
| Feature | DuPont schedule |
|---|---|
| Crews | 4 |
| Shift length | 12 hours, rotating between days and nights |
| Rotation cycle | 28 days (4 weeks) |
| Pattern | 4 nights, 3 off, 3 days, 1 off, 3 nights, 3 off, 4 days, 7 off |
| Average hours | 42 per week, 168 per cycle |
| Longest stretch on | 4 shifts |
| Longest break | 7 days in a row, once every cycle |
The 28-Day DuPont Rotation, Week by Week
Every crew follows the same four weeks. The crews simply start one week apart, which is why exactly one crew is always on days and one is always on nights. Here is the rotation with the cycle starting on a Monday.
| Crew | Week 1 | Week 2 | Week 3 | Week 4 |
|---|---|---|---|---|
| Crew A | 4 nights, 3 off | 3 days, 1 off, 3 nights | 3 off, 4 days | 7 off |
| Crew B | 3 days, 1 off, 3 nights | 3 off, 4 days | 7 off | 4 nights, 3 off |
| Crew C | 3 off, 4 days | 7 off | 4 nights, 3 off | 3 days, 1 off, 3 nights |
| Crew D | 7 off | 4 nights, 3 off | 3 days, 1 off, 3 nights | 3 off, 4 days |
Some employers publish the same rotation starting from a different week, for example with the four day shifts first. The sequence and the coverage are identical; only the starting point changes. If a contract or job posting lists the weeks in a different order, read it as a loop rather than a different schedule.
The 7-Day Break: DuPont's Biggest Selling Point
Once every 28 days, each crew gets a full week off. That is 13 built-in breaks a year. Employees use them for travel, family time, side businesses and recovery, and if they add a week of PTO next to the off week, they get two or more weeks away while using only one week of paid time off. In recruiting, "a week off every month" is one of the easiest benefits to explain, and it is a big reason the DuPont schedule survives in plants where other 12-hour patterns come and go.
For the business, the off week is predictable too. You always know which crew is away, which makes it a natural time to plan maintenance windows for equipment that the off crew normally runs, as long as you do not start calling people in on their week off. Once the off week stops being reliable, the main reason employees accept the hard parts of the schedule disappears.
The Hard Week: 72 Hours and a Quick Turnaround
The price of the week off is the second week of the cycle in the table above: 3 day shifts, 1 day off, then 3 night shifts. Within a calendar week that adds up to 72 hours, and the single day between the last day shift and the first night shift is a fast flip for the body clock. Employees often call it the hardest part of the schedule, and it is where fatigue-related mistakes are most likely.
NIOSH guidance on long work hours notes that long stretches of 12-hour shifts build fatigue and suggests avoiding several days of work followed by long breaks, which is exactly the trade DuPont makes. OSHA also warns that long and irregular shifts raise the risk of injuries and accidents. If you run DuPont, plan for that week on purpose: avoid scheduling training or extra shifts around it, keep breaks protected and be careful about asking anyone in that week to cover additional hours.
DuPont Schedule Hours and Overtime
DuPont averages 42 hours a week, but the weekly hours swing widely, from 0 to 72 depending on how the cycle lines up with your workweek. Federal overtime for non-exempt employees is calculated on hours over 40 in each workweek, and each workweek stands alone, so those swings create overtime even though the average is barely over 40.
| First day of the workweek falls on | Weekly hours in the cycle | Overtime hours per 28 days | Overtime hours per year (13 cycles) |
|---|---|---|---|
| Day 1 of the cycle | 48, 72, 48, 0 | 48 | 624 |
| Day 2 or day 7 | 48, 60, 48, 12 (or 60, 48, 12, 48) | 36 | 468 |
| Day 3 or day 6 | 48, 48, 48, 24 (or 48, 48, 24, 48) | 24 | 312 |
| Day 4 or day 5 | 48, 36, 48, 36 (or 36, 48, 36, 48) | 16 | 208 |
The overtime premium is the extra half of the regular rate for every overtime hour. For an employee paid $20 an hour, that is $10 per overtime hour on top of straight time. With the workweek starting on day 1 of the cycle, the premium is 48 × $10 = $480 every 28 days, or $6,240 a year. With the workweek starting on day 4 or day 5, it is 16 × $10 = $160 every 28 days, or $2,080 a year. Same employee, same shifts, same days off, and a $4,160 difference per employee per year.
Formulas
Average weekly hours = 14 shifts × 12 hours ÷ 4 weeks = 42
Overtime hours in a workweek = hours in that workweek − 40 (if more than 40)
Overtime premium = overtime hours × regular rate × 0.5
Annual hours per employee = 42 × 52 = 2,184
Federal rules treat the workweek as a fixed and regularly recurring 168-hour period, and it can only be changed if the change is meant to be permanent and is not designed to avoid overtime. So the lever to use is the rotation itself: before launch, choose which day the DuPont cycle starts relative to the workweek you already use, and test the options in the generator. If your night shifts carry a premium, include it in the regular rate for overtime; the shift differential calculator handles that math. Some states also have daily overtime rules for shifts over 8 or 12 hours, so review overtime laws by state before you set pay.
DuPont vs. Pitman vs. 4-On 4-Off
All three patterns cover 24/7 operations with four crews on 12-hour shifts and average 42 hours a week. The differences are in how the work and the time off are bunched together.
| DuPont | Pitman | 4-on 4-off | |
|---|---|---|---|
| Cycle | 28 days | 14 days | 8 days (16 if rotating) |
| Longest stretch on | 4 shifts | 3 shifts | 4 shifts |
| Longest break | 7 days | 3 days | 4 days |
| Days and nights | Rotates within the cycle | Usually fixed crews | Fixed or rotating |
| Hardest part | The 72-hour week and quick day-to-night flip | Built-in overtime every other week | Workdays drift through the week |
| Best for | Crews who value long breaks | Crews who value weekends and short stretches | Crews who want the simplest pattern |
Use the generator above to switch between the three and compare the "Hours by Workweek" tables side by side. For details on the other two, see the Pitman schedule guide and the 4-on 4-off schedule guide.
How Many Employees Do You Need for a DuPont Schedule?
Each round-the-clock position needs 168 hours of coverage a week, and each DuPont employee averages 42, so the minimum is 4 people per position, one on each crew. A control room that needs 3 operators on every shift needs 12 operators, 3 per crew.
Formula
Coverage hours per year = positions × 8,760
Available hours per employee = 2,184 − average PTO, sick and training hours
Employees needed = coverage hours per year ÷ available hours per employee
With 3 positions, coverage is 26,280 hours a year. If each employee loses about 156 hours a year to PTO, sick time and training, each one is available for 2,028 hours, and you need 26,280 ÷ 2,028, or about 13 people instead of 12. On DuPont, relief staff matter even more than on other patterns, because covering a gap usually means pulling someone out of their week off or extending the 72-hour week, which are the two things most likely to drive people to quit.
Pros of the DuPont Schedule
A full week off every cycle. Seven consecutive days off every 28 days is the longest built-in break of the common 24/7 patterns, and employees plan their lives around it.
Everyone shares nights. Because every crew rotates through days and nights, no crew is permanently stuck on the night shift, which many employees see as fairer.
Four crews and two shifts. Two 12-hour shifts mean one handoff fewer every day than three 8-hour shifts, and the same crew works together every shift.
Fewer days at work. Employees work about 182 days a year, which cuts commuting time and cost.
Predictable for years. Once a crew assignment is set, every workday is known well in advance, which makes vacation and family planning simple.
Cons of the DuPont Schedule
The 72-hour week. Seven 12-hour shifts in one calendar week, split by a single day off, is the toughest stretch in common shift scheduling.
Day-to-night switching. Rotating between days and nights within the cycle is harder on sleep than fixed shifts. Some employees never fully adjust.
Overtime swings. Weekly hours range from 0 to 72, so payroll costs vary from week to week and overtime is guaranteed unless the cycle is carefully lined up with the workweek.
Weekends depend on the cycle. Crews work about half of all weekends, often two in a row, and the weekends off are tied to the rotation rather than the calendar, which can be hard on families with school-age children.
Coverage is fragile. A call-out often means asking someone to give up part of their week off, which erodes trust in the schedule quickly.
Who Uses the DuPont Schedule?
| Industry | Why DuPont fits |
|---|---|
| Chemical and process plants | Where the pattern started; processes cannot stop and crews need deep familiarity with the equipment |
| Refineries and power plants | Continuous operation with stable crews and planned maintenance windows |
| Paper and steel mills | Twenty-four hour production with long-tenured crews who value the week off |
| Hospitals and emergency services | Twelve-hour shifts already common, and rotating nights spreads the load |
| Utilities and water treatment | Always-on facilities with small, specialized crews |
DuPont Schedule Template
Copy this 28-day template into a document or spreadsheet. Day 1 can be any day of the week; replace it with your own start date. For a calendar with real dates, shift times and weekly hours, use the generator above and click Copy for Excel.
| Day of cycle | Crew A | Crew B | Crew C | Crew D |
|---|---|---|---|---|
| 1 | Night | Day | Off | Off |
| 2 | Night | Day | Off | Off |
| 3 | Night | Day | Off | Off |
| 4 | Night | Off | Day | Off |
| 5 | Off | Night | Day | Off |
| 6 | Off | Night | Day | Off |
| 7 | Off | Night | Day | Off |
| 8 | Day | Off | Off | Night |
| 9 | Day | Off | Off | Night |
| 10 | Day | Off | Off | Night |
| 11 | Off | Day | Off | Night |
| 12 | Night | Day | Off | Off |
| 13 | Night | Day | Off | Off |
| 14 | Night | Day | Off | Off |
| 15 | Off | Off | Night | Day |
| 16 | Off | Off | Night | Day |
| 17 | Off | Off | Night | Day |
| 18 | Day | Off | Night | Off |
| 19 | Day | Off | Off | Night |
| 20 | Day | Off | Off | Night |
| 21 | Day | Off | Off | Night |
| 22 | Off | Night | Day | Off |
| 23 | Off | Night | Day | Off |
| 24 | Off | Night | Day | Off |
| 25 | Off | Night | Off | Day |
| 26 | Off | Off | Night | Day |
| 27 | Off | Off | Night | Day |
| 28 | Off | Off | Night | Day |
How to Make a DuPont Schedule Easier on Employees
Protect the off week. Treat the seven days off as the most valuable part of the schedule. Build a relief pool or cross-train other crews so that call-outs rarely touch someone's week off.
Plan around the hard week. Avoid scheduling mandatory training, meetings or extra shifts during the 72-hour week, and give supervisors extra attention to fatigue on the first night shifts after the quick turnaround.
Write a clear PTO rule. Decide whether a day of PTO equals 12 hours on a 12-hour schedule and how PTO interacts with the off week. Many employers let employees pair one week of PTO with the off week, and the policy should say so.
Keep handoffs tight. With crews rotating between days and nights, the same two crews rarely hand off to each other for long. Use written shift handoff notes so nothing is lost when a crew disappears for a week.
Ask for feedback after two cycles. Two full cycles is about two months, enough for employees to experience every part of the rotation twice. Adjust shift start times or handoff routines before the schedule becomes permanent.
How to Roll Out a DuPont Schedule
1. Confirm you need equal coverage around the clock
DuPont staffs every hour the same way. If your volume drops sharply at night or on weekends, an equal-coverage pattern may cost more than a schedule built around demand.
2. Choose the start day and check the overtime
Enter possible start dates in the generator with your existing payroll workweek, compare the "Hours by Workweek" tables and pick the start day before launch. Budget for the overtime that remains.
3. Build balanced crews
Spread skills, licenses and experience evenly so every crew can run the operation alone, including during the night shifts after the quick turnaround.
4. Write the policies
Cover shift times, meal and rest breaks, shift swaps, call-outs, holiday pay, PTO in 12-hour increments and how the off week is protected.
5. Give notice and pilot
Publish the full calendar weeks ahead, check any local predictive scheduling rules and run at least one full 28-day cycle as a pilot before making it permanent.
Common DuPont Schedule Mistakes
- Averaging hours across the cycle. A 72-hour week is a 72-hour week for overtime, even if the next week is zero.
- Lining the cycle up with the workweek by accident. Starting the rotation on the first day of your workweek produces the most overtime of any alignment.
- Calling people in on the off week. It solves one shift and damages trust in the whole schedule.
- Skipping relief staff. Four people per position leaves no room for vacations or sick days.
- Leaving night premiums out of overtime. Shift differentials belong in the regular rate.
- Ignoring fatigue in the hard week. The quick day-to-night switch is when mistakes and injuries are most likely.
Example: A Water Treatment Plant
A regional water treatment plant ran a fixed day and night schedule with 8-hour shifts and struggled to keep night operators. Most wanted days, and the night crew had the highest turnover in the facility. The operators' committee proposed the DuPont schedule because everyone would share nights and get a week off every month.
Before launch, the plant manager modeled the rotation with the plant's Sunday-to-Saturday payroll week. Starting the cycle on a Sunday put every crew at 72 hours in one week of each cycle and created 48 overtime hours per operator every 28 days. Starting the cycle on a Wednesday instead kept every crew's pattern and off week the same but cut the built-in overtime to 16 hours per cycle. The plant also cross-trained two lab technicians as relief operators so that call-outs would not cut into anyone's week off. A year later, night turnover had fallen, and the off week had become the first thing operators mentioned when recruiting friends.
Final Thoughts
The DuPont schedule covers every hour of the week with four crews and gives each crew a full week off every 28 days, which is why it has lasted for decades in plants that never stop. The cost is a demanding 72-hour week, a fast flip from days to nights and weekly hours that swing enough to create overtime. Lay out the rotation in the generator, line the cycle up carefully with your payroll workweek, protect the off week with relief staff and write clear rules for PTO and call-outs. Done well, DuPont is a schedule people stay for.
Run Your DuPont Schedule in Updoot
Updoot's scheduling software handles rotating shift operations like DuPont. You can assign employees to rotating shift patterns, attach each shift to a job and location, see approved PTO and availability while you build and spot overtime before you publish. Employees see their schedule on their phones, request swaps in the app and clock in to scheduled shifts with the built-in employee time clock, so you can compare scheduled and actual hours every week and export payroll-ready reports that handle weekly hours that swing from 0 to 72.
See the Updoot pricing page for current plans, and start free with your team.
Sources
- U.S. DOL Fact Sheet #23: Overtime Pay Requirements of the FLSA
- 29 CFR 778.105: Determining the Workweek
- OSHA: Long Work Hours, Extended or Irregular Shifts, and Worker Fatigue
- NIOSH Training for Nurses on Shift Work and Long Work Hours